A development facility may be agreed for £1.5 million, but that does not mean £1.5 million lands in your account on day one. For most ground-up, conversion and major refurbishment schemes, the development drawdown process releases funds in stages against work completed, verified costs and the lender’s view of what remains to be done.
That structure protects the lender, but it also protects a developer from starting a build with an unrealistic funding plan. The key is making sure the facility, cash flow forecast and build programme all say the same thing before contracts are exchanged.
What is the development drawdown process?
A development loan is usually split into an initial advance and a series of later drawdowns. The initial advance may fund land or property acquisition, repay an existing lender and cover agreed professional fees. The remaining facility is released during the build, commonly monthly or at defined construction milestones.
Each release is based on more than an invoice. The lender wants evidence that the claimed work has been completed, that the scheme remains within budget and programme, and that enough money is left to finish it. A monitoring surveyor, often called a quantity surveyor or QS, normally provides that independent assessment.
The lender will also look at its security position. Development finance is commonly assessed against a combination of day-one loan-to-value (LTV), total loan-to-cost and gross development value (GDV). Day-one LTV is the debt as a percentage of the site’s current value at completion. GDV is the expected value once the scheme is finished. A strong GDV does not remove the need for sensible day-one leverage and a fully evidenced cost plan.
Before the first drawdown: what lenders need
The drawdown process begins at underwriting, not when the builder submits the first invoice. The lender needs a clear picture of the project, the borrowing entity and the planned exit.
For a straightforward site, that normally means planning documentation, purchase contract, valuation, build cost schedule, programme, contractor details, professional team information and a cash flow forecast. Where planning is still pending, or conditions remain outstanding, the funding route may need to be structured differently. A lender may lend on the existing value initially and release further money only once planning or another condition has been satisfied.
The build cost schedule matters particularly. It should separate hard construction costs from professional fees, statutory connections, warranties, contingency, marketing and finance costs. It should also show when each cost is expected to fall due. A lender may accept a contingency, but it will not treat an unexplained contingency as a substitute for a detailed budget.
Legal work runs alongside valuation and underwriting. Solicitors will confirm title, planning position, security, company authority where an SPV is borrowing, and the terms on which funds can be released. If another charge already exists, the lender will need an agreed repayment or priority arrangement. Delays at this stage are often administrative rather than commercial, but they can still hold up a start date.
How each staged drawdown is assessed
Once the facility has completed, the developer submits a drawdown request. The precise format varies, but it usually includes a summary of work completed, invoices or a payment schedule, updated costs to complete and confirmation of the amount requested.
The QS visits the site or reviews the evidence required by the lender. They assess the value of work done, compare progress with the agreed programme and identify whether the remaining facility is sufficient to complete the project. Their report recommends the amount available for release, subject to the lender’s conditions.
The lender then reviews the report and checks that there has been no material adverse change. A drawdown may be reduced or delayed where work is behind programme, costs have increased, planning has not been complied with, insurance has lapsed or an earlier release was used outside the agreed purpose.
Funds can be paid to the borrower, solicitor or, in some structures, directly to contractors. It depends on the lender, the project risk and what was agreed at completion. Developers should not assume a request submitted on Friday will fund a subcontractor on Monday. Build in time for the QS inspection, report, lender sign-off and payment processing.
Cost to complete is the crucial calculation
The central question is simple: after this drawdown, is there still enough committed finance and developer cash to finish the scheme?
A project can appear profitable on a GDV basis while still facing a cash flow problem halfway through. For example, a £500,000 conversion with a £750,000 projected GDV may be viable in principle, but not if an unexpected £75,000 of structural works consumes the contingency before first fix. If the lender’s maximum facility has been reached, the developer may need to inject equity, renegotiate the scope, source additional finance or pause works. None of those options is ideal once contractors are on site.
This is why a sensible facility is not simply the one with the highest headline GDV leverage. The right structure reflects acquisition cost, build costs, interest, fees, contingency, the programme and the cash you can genuinely contribute if something moves.
Interest and fees during the build
Development finance interest may be retained, rolled up or serviced. Retained interest is usually set aside from the facility at completion to cover projected interest payments. Rolled-up interest accrues and is repaid at exit, increasing the total debt over time. Serviced interest is paid monthly by the borrower from separate cash flow.
Each option has a trade-off. Retained or rolled-up interest can preserve cash during construction, but it reduces net funds available for the scheme or increases the redemption balance. Serviced interest can improve the overall debt position, but it demands dependable monthly income. The lender’s calculation will also include arrangement fees, monitoring surveyor fees, valuation, legal costs and, where relevant, exit fees.
It is worth modelling the facility against a slower build as well as the intended programme. A six-month delay can affect monitoring costs, interest, sales costs and the timing of refinance. A credible exit must remain credible under that pressure.
Where development drawdowns commonly stall
From our experience arranging developer finance, the most common issue is not a lack of appetite at the outset. It is a mismatch between the original appraisal and the live project. Underwriters and QSs regularly query vague contractor quotes, missing invoices, costs labelled as completed when materials are merely ordered, and programmes that have not been updated after a delay.
Another frequent problem is treating the final drawdown as guaranteed because the overall facility was agreed. It is not automatic. If the monitoring report identifies a funding gap or a significant departure from the approved scheme, the lender will want a plan before releasing more money. Early communication is far better than presenting the issue after contractors have stopped work.
Keep a live cost report, not just the spreadsheet used to secure the loan. Record committed costs, paid costs, variations, contingency remaining and projected completion date. If the scheme changes, tell the lender and QS promptly. A manageable variation is easier to assess when the evidence is current.
Planning the exit before the build starts
Most development facilities are short-term and need a defined exit. That may be sale of the completed units, refinance onto a buy-to-let or commercial mortgage, or a development exit facility that repays the construction lender while sales complete.
Sales exits depend on realistic pricing, absorption rates and the condition of the local market. Refinance exits depend on the completed valuation, rental income, borrower profile and the new lender’s criteria. Do not base the entire exit on the highest estate agent estimate or a mortgage product that may not suit the finished property.
A development exit facility can be useful where works are complete but sales need more time. It is still borrowing, with its own costs and underwriting requirements, rather than an automatic extension. Starting those conversations well before practical completion gives you more options.
If you are assessing a site, speak to a specialist adviser before committing to the purchase. A properly structured facility should match the build programme, the drawdown profile and the exit, rather than leaving you to bridge a funding gap mid-project. Lending is subject to status, valuation and lender criteria. Unregulated bridging, buy-to-let and most development finance are not regulated by the Financial Conduct Authority.
Laurence Penn is a mortgage and protection adviser at Your Financial Assurance Ltd, a directly FCA-authorised brokerage (FRN 1052118) trading since 2011. He specialises in bridging loans, second charge mortgages and developer finance, alongside residential, buy-to-let and complex-income mortgage cases. He advises clients across London and the Home Counties, and arranges specialist property finance UK-wide.
Important information
This article is general information only and does not constitute personal advice or a recommendation. All lending is subject to status, valuation, lender criteria and affordability. Rates, fees and terms vary by lender and by case.
Your home may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it. Your Financial Assurance Ltd is Authorised and Regulated by the Financial Conduct Authority. FRN 1052118.